BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
The awarded framework agreement will ensure TfGM can meet its legal requirements to maintain a safe estate and reduce resource implications whilst ensuring TfGM is not committed to any spend. This will ensure TfGM FM can continue to ‘run our business’ and improve and enhance our estate to ensure we deliver against the ‘Future Ready’ business pillar
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Argyle Construction | - | - | 1 lot Lot 1 | - |
| AT Nolan | - | - | 1 lot Lot 1 | - |
| Jamieson Contracting | 04253085 | - | 1 lot Lot 1 | - |
| Schofield and Sons | 02459259 | - | 1 lot Lot 1 | - |
| Seddon Construction | 03578140 | - | 1 lot Lot 1 | - |
| Simon Dean Electrical | - | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 12 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 720 days (≈2 yrs) | £3,360,000 initial term | 6 | AT Nolan Schofield and Sons Seddon Construction Jamieson Contracting Argyle Construction Simon Dean Electrical | active |
Weightings from the notice.
Government spending data: These suppliers have received £27,632,594 in 229 payments (over £25k) from Department for Work and Pensions, Worcestershire Acute Hospitals NHS Trust, Greater Manchester Combined Authority, Staffordshire Police, Ministry of Justice and 3 more public bodies (2017-06-15 to 2026-06-15).
Published by the buyer on this notice. Check the original notice — details change and are not updated here.