The proposed Sutton Bank 2023 annual maintenance works include:
1. completion of the annual rock slope inspection of Upper Slope, Mid Slope and Lower slope and Cragg House slope by WSP engineer.
2. Clear vegetation and complete general scaling works from crest to the toe of the upper and lower rock face.
3. Routine maintenance of rock mesh / bolts to be undertaken, for example the removal of rock debris which accumulates in excess of 0.75m per metre run of mesh.
4. Inspection of 2022 remedial works to determine if advanced corrosion of any components is occurring.