Scheme covers 11.829lkm of surfacing across all lanes on both carriageways and involves resurfacing to 50mm with 110mm at previous loop locations. The bridge decks have been removed from this scheme and surfacing should stop +/- 5m from the joints.
All loops are redundant, road markings and studs to be replaced throughout.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| DSD Construction | 02818677 | £1,014,155 | - |