The construction of concrete bases and associated works in preparation for Metrostor bin enclosures to be installed by others. The works are at 3nr individual flatted block sites in Runcorn. 1-19 Companys Close, 53 -84 Coronation Road , 3-33 Lavender Close.
It is anticipated that the pre start meeting with the successful contractor will take place by 19/11/20. The successful contractor will be required to programme the site works to achieve commencement on 30/11/20 and completion of all works by no later than 18/12/20, 3 calendar weeks.
The successful contractor is an SME
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Sterling Services (Northern) Ltd | 05899577 | £45,000 | - |