BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
The specific Project and Contract Management Support Services required in respect of the delivery of part ERDF funded Project MUNIO relate to the provision of:
1)Development of ECC Tender Documentation
2)Support throughout Contractor Tender Process & Award of Contract
3)Cost Management Services
4)ECC Project Management Services
5)Programme and Risk Management
The initial contract period for Munio Mill Fleam-Part 1 is 30 months.
The contract is estimated to commence 17th August 2020 and end on 31 January 2023.
It is to be noted that the ERDF funding programme which is partially covering the costs of these works will cease in December 2023.
There is a maximum budget of £350,000 for Munio Mill Fleam -part 1
Please note, suppliers wishing to express interest and obtain the documentation, must do so by 15:00 on 19 July 2020. It is recommended that you express interest and obtain the documentation well before this time to allow sufficient time to prepare and submit a comprehensive response. The deadline for returns is 14:00 on 20th July 2020. Please visit the Councils e-tendering system https://www.eastmidstenders.org where you can express interest and obtain the documents, (please note we will only accept expressions of interest through the e-tendering system
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Arcadis Consulting (UK) Limited | 02212959 | £350,000 | - |
Government spending data: This supplier has received £176,574,950 in 2,094 payments (over £25k) from Department for Transport, DEFRA, BEIS, Ministry of Defence, Welsh Government and 16 more public bodies (2015-10-16 to 2026-06-19). View full payment history →