BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
Contract for AAU Substation High and Low Voltage Upgrades at West Hertfordshire Teaching Hospitals NHS Trust (WHTHT).
The project relates specifically to the requirements for the Substation's additional High Voltage
Transformer and new Low Voltage Switchboard currently supporting the AAU Building's electrical infrastructure at Watford General Hospital.
The Specification was specifically prepared for the Design, Manufacture, supply, delivery, off-loading, placing in situ, re-assembly, testing and commissioning of the new transformer, low voltage switchboards, and interconnecting busbar.
This contract was awarded via a below threshold works tender in line with Trust Standing Financial Instructions.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Playfords Limited | 00203301 | £900,000 | - |
Government spending data: This supplier has received £3,147,933 in 207 payments (over £25k) from Guy's and St Thomas' NHS FT, United Lincolnshire Hospitals NHS Trust, Cambridgeshire Constabulary, Bedfordshire Police (2021-04-22 to 2026-02-27). View full payment history →