The works comprised, but not be limited to:
The construction of a new 2-storey building (approximately 2 800 m2) at the front of the hospital site.
N.B. The first floor will not be fitted out and will be constructed to a shell standard only.
Refurbishment of an existing ground floor department (approximately 1 425 m2).
Reconfiguration of existing access ways and new paved areas.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Barnes Construction | 02793892 | £12,680,096 | - |