NOTIFICATION OF SUBCONTRACT PACKAGE
A47 / A11 Thickthorn Interchange
Galliford Try, as the East Region Delivery Partner are delivering the A47 / A11 Thickthorn Interchange project in the county of Norfolk in partnership with Highways England. The project will help relieve congestion at Thickthorn junction by providing two new free-flowing slip roads that will connect the A47 with the A11. The new slip roads will re-route traffic away from the junction and flow it under new underpasses.
The project has recently submitted a Development Consent Order to the Planning Inspectorate and the project is forecast to commence on site in early 2023 and will take around 2 years to complete.
Package: Ground Penetrating Radar (GPR)
Outline Scope of Works
A GPR survey is required of the full site to locate any and all potential services prior to the construction works starting in 2023.
The required output from the survey is a 2D and 3D model. The 3D model needs to be in a format that can be incorporated into the full site model.
This survey will focus on the offline areas of the project. Any online elements will be instructed separately.
Principal Activities Approximate Quantities
Completion of onsite GPR survey and 2D&3D model output. 1no
Programme
It is currently anticipated that these works will commence in June or July 2022.
Timings
Deadline for Notifications of Interest 16:00 hrs on Friday 10th June 2022
Galliford Try procurement process
To secure work with Galliford Try, a supplier will need to pass the PAS91 onboarding process administered through Builders Profile. Details will be shared with shortlisted suppliers.
If this package is of interest to your company please contact our procurement team by e-mail on …@4projectsmail.com by the above deadline with your notification of interest and details of your capabilities.
Any notifications of interest after the above deadline will not be responded to.