BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
Balfour Beatty VINCI (BBV) have been awarded HS2 main works civils contracts, lots N1 and N2 under an Early Contractor Involvement contract (ECI). We are currently in stage one of a two stage process.
We are looking to engage with the Scaffold supply chain whom provide temporary scaffold works.
Examples of the work required are as follows:-
*Access platforms on top of pile caps and sheet piles
*Standard scaffolding
*Guardrails to secure pile caps
*Working Platforms
*Stairs into excavations
Pedestrian barriers at the top of batters
Full details and specifications will be provided to the successfully shortlisted suppliers. Suppliers should be aware of the scale of this project and should assess their internal capabilities to be able to carry out the intended scope of works, prior to completing this expression of interest (EOI).
No supplier information available.