There has been a number of changes to the Hillingdon Hospital Masterplan project that have increased both the scope and the programme of RIBA Stage 2, extending it by an additional circa 12 months. The appointed supplier will have to manage the project during this period, April 2021 to end of March 2022.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Ridge and Partners LLP | OC309402 | £334,397 | - |
Government spending data: This supplier has received £5,228,760 in 425 payments (over £25k) from Wiltshire Police, HMRC, FCDO, UK Health Security Agency, Department of Health and Social Care and 7 more public bodies (2020-01-10 to 2026-06-03). View full payment history →