The contract is to replace the air conditioning to Conference Rooms 1 & 2 at Beech Hurst, SP10 3AJ
The works require making good to all areas adjacent to the work for a full and complete installation.
The Main Contractor is required to programme and co-ordinate the work of all subcontractors and should plan for the works to be completed in 6 weeks.
The works must be carried out in strict accordance with the drawings and other tender documents which will ensure the obligations set out under planning permission relating to the window replacement are met.
Further details are available at https://uk.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=89064&B=UK