The project consists of 115 New Build Residential units over 8 floors. Piled foundations, RC frames and different envelope types. The project duration is 82 weeks, and anticipated start date is September 2020 with anticipated completion in February 2022. Claritas Group is the Construction Manager and any successful Contract will be let between Medway Council and the Trade Contractor. This opportunity is for the appointment of PILING contractor.Tender documents are available via the Kent Business Portal.