The works will comprise of, carefully breaking out existing macadam footpath including kerb edgings and excavate to reduce levels to allow for new footings, kerb edgings, new channel drains and macadam footpaths. Works also include for resurfacing and drainage repair works to the footpath area and the installation of a new aluminium door to the same elevation, including all enabling works
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Thomas Kershaw Builders Ltd | 01809894 | £20,000 | - |