Scope of Work:
Internal and external lifting will be required in identified locations. Most of the vertical lifting will occur alongside the completion of permanent works which in return requires the Subcontractor to carefully plan the methodology to avoid damaging permanent works. It will also require coordination and communication with the various Fit-Out and MEPH Contractors and Others to understand programme constraints, sequencing of works, The strategy shall also allow for the speedy mobilisation, relocation and demobilisation of Equipment to move materials, plant, and equipment to suit the Contractor's programme requirements.