Program - Works to be carried out between 25 July 2022 and 20/01/23 [26 weeks]. It should be noted that the temporary/permanent deck element of the building project must be completed by 20 August 2022.
Location - Atrium and adjacent plant room areas at Milton College; Chaffron Way Campus
Woughton Campus West, Leadenhall, MK6 5LP.
Works - to install a temporary [or permanent] crash deck floor above the second-floor gantry level of the atrium; to install a sacrificial waterproof deck on the floor and install guttering & storm water drainage; to form a new access to the plantrooms/floor; strip out redundant ventilation plant; new plant room works; removal of the atrium glazing; pigeon protection works.
Contract/procurement - Single stage contract traditional IFC JCT contract with contractor's design portion.
Tender period - 20 June 2022 - 15 July 2022
Consultant team - Client Representative/Project Manager - Project Management Solutions; Architect/Principal Designer - Devonshire Architects; Structural Consultant - SOLUTION CE; M&E Consultant - Panda CE; Approved Inspector - LEXICON
Tender packs are available from Craig Pullen (…@cpconsulting.org.uk)
Site visits are available on 4th, 5th & 8th July - details are in the tender pack.
Additional information: Tender packs are available from Craig Pullen (…@cpconsulting.org.uk)
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| T&B (Contractors) Ltd | 01667869 | £301,722 | - |
Government spending data: This supplier has received £8,542,515 in 59 payments (over £25k) from Department for Education, Barking, Havering and Redbridge University Hospitals NHS Trust, Metropolitan Police (2017-07-10 to 2025-10-08). View full payment history →