The scope for this package is the supply of 571 no. precast reinforced-concrete noise barrier panels, which will form part of the noise barrier structure to be constructed along the north and south sides of the High Speed Two (HS2) trace at the West Ruislip retained embankment and the Gatemead embankment. The noise barrier structure will also be constructed across the River Pinn Underbridge (RPU) and the Breakspear Road Underbridge (BRSU) structures. The breakdown of the required number of precast reinforced-concrete noise barrier panels is as follows:
The attached drawing provides a visual representation of the proposed noise barrier structure.
The goods are to include lifting points (hooks/eyes/etc.) and tie-in points for temporary works purposes.
The services are:
There may also be a requirement for storage space, depending upon the proposals for the noise barrier panels to be delivered on a just-in-time basis.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Explore Industrial Park | - | £4,100,000 | - |