Hillingdon Council is working to transform its approach to place-making and asset management, taking a proactive approach to support the delivery of wider corporate objectives. To effectively navigate these challenges and opportunities, the council is seeking to commission the combined development of a Local Growth Plan and Strategic Asset Management Plan to support its place ambitions.
This project brief proposes two work packages intended to run concurrently. The tender should be priced by package, and the costs for each stage of work should be set out across a 30-week programme.
Package 1: Local Growth Plan
Stage 1: Baseline Assessment
Stage 2: Identify Growth Priorities
Stage 3: Local Growth Plan and Capacity Review
Package 2: Strategic Asset Review
Stage 1: Initial Assessment
Stage 2: Strategic Asset Management Plan
Proposed Contract Start Date - 1st June 2025
Estimated Project Budget - £150,000
The full tender opportunty is advertised via our e-tendering platform (https://supplierlive.proactisp2p.com/Account/Login)
Ref-RFX1000046