Quotes requested from 5 suppliers on 16/07/2021.
Winning quote received on 19/07/2021
Outcome required /
Description of works:
400 metres of improved surafce on the marriotts way. Surface scrape of existing material, installation of adequate drainage to manage peak flow events. Removal of bollards, granite sub-base topped off by granite dust and mechanically tamped down to provide an improved walked, cycled and ridden surface
Completing works will result in:
Access for all, improved access during winter months
Waste:
surface materials from surface scrape - to create a habitat pile
Location: TG 09745 19137
Location Map Included in quote documents
Contractor accesses / other detail in order for quote:
400 metres of improved walking / cycling and riding surface. Granite sub-base blinded off with granite dust and mechanically tamped down.
CAD Drawings:
Included in quote documents if required
Timetable:
Deadline for delivery of improvements: By end of October 2021
Contractor quote Subcontracting clause
Quote evaluation: 60 % Cost - 20 % Experience of Delivery of similar projects - 20 % delilvery within desired timeframe
Deadline for submission: 17:00 on 30 July 2021 (will be reviewed on 2 August 2021)
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| J W RILEY CONTRACTING LIMITED | 10620165 | £39,759 | - |