Remedial work to slopes and repairs to amphibian fencing etc as described on drawings HW00590/3000/88 Rev 1 (Location 1 on Location Plan) and HW00590/3000/87 Rev 1 (Location 2 on Location Plan) and in the schedules.
The successful contractor would act as Sub-Contractor to Via East Midlands Ltd (Principal Contractor) under CDM Regulations.
Sub-contractors must be Accredited Installers of Flexterra HP-FGM.
Cost to include allowance for sub-contractor to re-apply the hydro-mulch if less than 80% establishment of grass cover over the slopes during the initial establishment period.
5% of the value to be withheld until after the first cut.
Information to be returned with the quote:-
Attachments:-
Location Plan
Drawing HW00590/3000/87 Rev 1
Drawing HW00590/3000/88 Rev 1
Schedules to be priced .
Additional information:
Please arrange for a site meeting on Tuesday 6th August or Thursday 8th August 2024 @ 10:00, directly with Nancy Ashbridge on tel: 01159772170 or email: …@viaem.co.uk
No supplier information available.