Loading contract…
BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
The works will comprise, but not be limited to:
The construction of a new 2-storey building (approximately 2 800 m2) at the front of the hospital site.
N.B. The first floor will not be fitted out and will be constructed to a shell standard only.
Refurbishment of an existing ground floor department (approximately 1 425 m2).
Reconfiguration of existing access ways and new paved areas.
No supplier information available.