The ORR needs a clear understanding that digital signalling proposals are being managed appropriately and can be supported in the Periodic Review1 process.
We require a specialist team to assess and report on Network Rail's signalling renewals plan with a particular focus on:
-Long-Term Deployment Plan (LTDP)
-Target 190plus research and development programme.
The specialist team will provide advice to us on the following areas:
â¢Decision making processes within Network Rail on the signalling renewals programme;
â¢signalling renewals projects planned in CP7 and the associated risks and opportunities;
â¢interfaces between conventional-partial signalling renewals, digital-ready renewals and digital renewals;
â¢commitments in the LTDP for CP7 and beyond and the critical path for delivery; and
â¢how Network Rail has evidenced benefits through its T190plus research and development programme.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| turner and townsend consulting limited | 03154483 | £80,000 | - |
Government spending data: This supplier has received £27,716,879 in 391 payments (over £25k) from Ministry of Defence, Scottish Government (2024-04-03 to 2026-03-30). View full payment history →