To successfully dismantle the existing Gatehouse bridge soffit and middle pier to install a new wider span bridge slab including new concrete abutments and invert. Grinton Little bridge requires existing material removed from under the bridge to aid for a new concrete invert as well as scour protection works to the training walls.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Thomas Armstrong (Construction) Ltd | 00818913 | £139,620 | - |
Government spending data: This supplier has received £4,968,132 in 70 payments (over £25k) from Cumbria Constabulary, Forestry Commission (2018-03-29 to 2025-08-01). View full payment history →