Leeds Bradford Airport is seeking to appoint a suitable Main Contractor to work on a design and build project to enhance the facilities and passenger experience through:
⢠Re-planning of the Passenger Search Area, and modelling to demonstrate capacity to manage 6.8 MPPA in line with the DfT 2024 compliance requirements.
⢠Arrivals Baggage offload / passenger routes resolved with utilisation of basement for arrivals baggage offload.
⢠Additional Reclaim carousels, and relocated immigration hall integrated into the Layouts
⢠New Retail layouts provided in outline
⢠PRM routes to enable enjoyment of the whole of the LBA passenger experience.
⢠Improved vertical circulation cores and routes.
Further details are provided in the RIBA Stage 2 report issued as part of the PQQ process. It is currently intended that works will be delivered over two phases:
1. Phase 1 - New Build Arrivals Terminal Building (approximately £28.5m budget cost)
2. Phase 2 - Remodelling to the existing Terminal (approximately £27.4m budget cost)
In addition to this there is circa £3.3m of ancillary works to support the phases above that will from part of the overall project. Client fitout works of circa £8m in value will need to be considered in the coordination of the design
Additional information: Documents can be accessed at https://in-tendhost.co.uk/intendsharedservices/
Is a Recurrent Procurement Type? : No
No supplier information available.