Design and Build contract for flood alleviation project at Holme\r
Stage 1 'Design' only to be awarded 17/11/2020\r
Following the completion of Stage 1 a decision will be made based on price whether to award stage 2 construction to the contractor.\r
Stage 2 Build - awarded 18/06/2021
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Eric Wright Civil Engineering Ltd | 02565379 | £405,500 | - |
Government spending data: This supplier has received £1,390,254 in 28 payments (over £25k) from Greater Manchester Combined Authority, Department for Transport (2014-11-03 to 2024-05-16). View full payment history →