Brief scope of works:
Strip out the following services and replace with new as per the design drawings and specification.
o Main air handling plant in the central ceiling plant room o LPHW boilers, pipework, flues, pumps etc. serving LPHW heating coils in the AHUs in the main central plant room o Controls system serving all existing plant and equipment o Ductwork as required ONLY within the plant room to enable the new installations to proceed.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Bower Fuller | 04904537 | £200,000 | - |