The works will make provision for the demolition of the existing facilities within the scope and the construction of a new video conference centre, comprising 8 no. 32'' screen VCC rooms
(for a single occupant), 3 no. face-to-face rooms (for a single inmate and visitor), 1 no. 43'' screen VCC rooms (for single occupant - EA compliant), 4 no. 43'' screen VCC room (for two occupants), 1 no. VCC office suite with tea point, 1 no. new EA-compliant WC, 1 no. data room, and external plant space. During the period of construction, 8 no. temporary legal visit spaces will be constructed on the First Floor, in the main public visits area.
A constructor has been appointed for the design and build of the project.
This is a two stage Design and Build Contract let under the PPC2000 (Amended 2013) Form of contract.
The original estimated value of the contract was calculated by MOJ, and its Cost Consultants following desktop and non-intrusive surveys and was based on information reasonably known at the time and arrived at via a thorough and appropriate methodology.
The first stage will involve the constructor providing Pre-construction surveys and design services at a cost of £33,2829.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Galliford Try Construction (UK) Ltd | SC209666 | £1,500,000 | - |
Government spending data: This supplier has received £105,774,066 in 136 payments (over £25k) from Ministry of Defence (2020-02-06 to 2025-07-01). View full payment history →