BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
Unitas are looking to appoint appoint Subcontractors to carry out the works under our overall supervision. The works are separated out into seven lots as follows;
LOT 1 Asbestos Removal
LOT 2 Scaffolding
LOT 3 Roofing Works
LOT 4 General Building
LOT 5 Electrical
LOT 6 Kitchens and Bathrooms
LOT 7 Post Completion Cleaning
Overall description of works to 39nr properties is as follows:
Re-roofing, leadwork renewal, replacement soffits, fascia's, guttering, pointing repairs, installation of SFS POD weatherboard system, renewal of entrance doors and store doors, installation of low level lighting, hard-wired smoke and heat detection and mechanical extractors and renewal and topping up of loft insulation.
No supplier information available.