Quotes sought from five suppliers by email on 05/10/2021.
Deadline for submission of quote: 31/10/2021
Completion Date: Spring/Summer 2022
Reason for works:
Complaints are received on Public Right of Way Sheringham Footpath 27 (Butts Lane) on an annual basis due to the path getting wet in winter.
Location: TG 14591 41901 , 52.931605 , 1.1914532 relies.improving.spends to
TG 15467 42101 , 52.933046 , 1.2045882 , bystander.assess.memory
Description of works:
⢠1.5m wide 950m long path is to be created along Butts Lane, Sheringham.
⢠100mm scrape will be made to the path to level the surface.
⢠geotextile layer will be installed at the base and will be topped with 100mm layer of Type 1 granite.
⢠Timber board edging will be installed along both sides of the path.
⢠Granite fines will be used to top the surface and will then be mechanically tamped to create a weatherproof surface.
Assumed items: The contractor is expected to deliver all materials to site to allow the construction to be delivered successfully.
Delivered Outputs/Outcomes:
1. 1.5metre wide X 950metre long footpath improvement
2. Vegetation knockback on either side to improve access for all users.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| MACKHOUSE LANDFILL SOLUTIONS LTD | 10550947 | £39,499 | - |