Skanska SAS13 Bridge Replacement - Rail Systems WP03.2 Scope
1) Signalling:
Assets to be disconnected and reinstated during blockade:
Cabling to be Disconnected and Renewed:
2) Telecoms:
Cable replacement Fibre Optic and copper:
Testing of Signalling cables:
3) E&P (LV)
240V DNO Power Supply to Star City TEH
Diversion in temporary route:
600lm Cable Installation through existingDBP3 Cess Trough Route, 5 Track UTX, 2no. URX's and elevated trough route.
Testing and commissioning of supply and EIS of THE DNO Power.
Cable Diversion in New Route:
600lm Cable Installation through existing DBP3 Cess Trough Route, New Viaduct Cable Route and 1 no. Dual Track UTX.
Removal of Temporary DNO Cabling
4) Track:
Stage 1 Track - Pre Blockade - Weekend Disruptive Possessions:
Stage 2 Track - Main Blockade
All Track Works Include:
5) Civils:
Dual Track UTX:
Installation during Blockade, 6 Way Multiduct, 2 no. 1.2m proprietary chambers. Circa 12m Long
Track Side S&T Route
100lm of TTS 200 or similar Troughing in Cess, inc 2 no. connections to UTX.
Temporary S&T Route
300lm Cable Trough Route Removal
6)
Supply of Track, Signalling, Telecoms & E&P CRE for Works
Supply of Signalling and Telecoms Testers for Works
Supply of Rail System Manager, embedded within SAS 13 Project Team to Manage all Rail Systems Disciples
Tenderers will be issued a formal invitation to tender (ITT) with a pricing and submission document to complete.
The submission will included a balanced scorecard requesting answers to questions (along with evidence) to be submitted for review and scoring. The highest scoring tenderers will be considered preferred tenderer for the works. High level criterial of the balanced scorecard questions will include:
Health & Safety
Quality
Sustainability
Environmental
Competence
Capability
Capacity
Commercial Price
Mid tender reviews will be held prior to the submission deadline to review the scope of works with the SAS13 project team. Following the submission deadline, there will be post tender reviews to review your submissions with the SAS13 project team.
Best and final offers may be requested from tenderers.
Skanska have been employed by Network Rail (NR) to replace the existing SAS 13 bridge to increase lateral clearance below the structure to enable the construction of HS2's new depot access lines and access to the new HS2 depot via road. The existing bridge forms the rail intersection between the Stechford to Aston (SAS) line and the Birmingham to Derby Line (DBP3).
The new bridge will be a 92m single spanning structure. Skanska's appointment by Network Rail includes the design and demolition of the existing bridge and installation of the new structure.
No supplier information available.