The scope of services shall involve performing the necessary adaption works to alter the existing layout and provisions to achieve a learning environment suitable for the end user. The building will be partially occupied by the end-user and so the Contractor will be responsible for phasing the works around the schools activities ensuring close liaison to prevent any incidents. This includes the following specific items:
Internals
Adaption works to create the following spaces;
⢠Installation of new partitions to divide existing rooms and create additional areas
⢠Installation of new teaching walls complete with additional electrical and data outlets, interactive white boards etc. Contractor will be responsible for the design and install of all MEPH works, this will be a CDP item under the contract
⢠Isolated structural works to open up space for new use
⢠Installation of new worktops and sinks to specialist teaching spaces
⢠Isolated redecoration and renewal of floor coverings
⢠Adapt existing pipework runs in relation to changes to sanitaryware layouts
⢠Supply and installation of roller blinds to isolated areas
⢠Design and installation of new Science Classroom. This will be a CDP item under the contract to be undertaken by the Main Contractors specialist sub-contractor.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Logan Construction Ltd | 02968000 | £205,000 | - |
Government spending data: This supplier has received £22,939,560 in 112 payments (over £25k) from London Ambulance Service NHS Trust, Cabinet Office, Guy's and St Thomas' NHS FT, HMRC, Barking, Havering and Redbridge University Hospitals NHS Trust (2021-04-09 to 2025-09-25). View full payment history →