Northern has 10 class 158/9s that based on the time between overhaul (8 years) need to go through a C6 overhaul line with Northern's & Eversholt specification document "EV/VI1586
Issue 3".
The requirement is that each of the 10 units has been through the C6 overhaul programme before the current C6 expires as per the below dates;
Unit No Exam Due Date
U158910 C6 03/09/2024
U158907 C6 23/09/2024
U158906 C6 14/10/2024
U158901 C6 04/11/2024
U158905 C6 25/11/2024
U158902 C6 16/12/2024
U158903 C6 20/01/2025
U158909 C6 03/02/2025
U158904 C6 02/03/2025
U158908 C6 29/03/2025
The C6 focus' on; AIR SYSTEM (Excluding brake equipment)/ BRAKES - AIR/VACUUM/
BODYWORK (Excluding interior trim)/ BATTERY/CONTROL SYSTEMS/ FLOORING/
HEATING/AIR CONDITIONING/ INTERIOR TRIM /FITTINGS/ FUEL SYSTEMS/ DOORS/
UNDERFRAME/ VEHICLE ACTIVITIES/ WATER & TOILET SYSTEMS (excluding Catering).
Additional information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement.