BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
Removal of existing non compliant external wall insulation and replacement with a compliant system to all external elavations. The work is to be carried out to a four storey purpose built homeless hostel located in the centre of Bristol City with residents in occupance throughout the full duration of the works. It is likely the hostel will be at full capacity throughout all of the works.
The process is being overseen by SAHA Consulant Pellings, for further details please contact
Gary Reynolds, Partner FCIOB, FRICS
Tel ; 0208 460 9114
Email ; …@pellings.co.uk
Additional information: Please field all queries to SAHA Consultant Pellings whom is appointed Contract Administrator for the above proposed works.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| SUSTAINABLE BUILDING SERVICES (UK) LIMITED | 01382149 | £412,000 | - |