Beech Hurst is the headquarters building for Test Valley Borough Council (TVBC) with four number plant rooms located at third floor level, with restricted access from the mezzanine floor. Each plant room contains three gas modular boilers providing heating to each corner of the building (NE, NW, SE, and SW)
The project comprises of the replacement of the existing Gas fired modular boilers installed in the region of 30 years ago with new modern energy efficient LPHW gas boilers and flues, together with new Building Management Control (BMS) package, weather compensation technology and optimised controls. Including all builders work in conjunction with these works.
The selected contractor will be responsible for all aspects of the delivery of works and the co-ordination of all sub-contractors.
It is intended that the works be carried out in two phases over the summer of 2020 carrying out works to two boiler rooms at any one time. The contractors attention is drawn to the fact that the office will be fully open during the contract period; method statements and previous experience submitted should reflect these and all other relevant facts.
Full information can be accessed on our eTendering system at https://uk.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=32704&B=UK
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Corrigenda Ltd | 03920337 | £341,605 | - |
Government spending data: This supplier has received £254,876 in 23 payments (over £25k) from Hampshire & Isle of Wight Constabulary, Salisbury NHS Foundation Trust, Thames Valley Police, Department for Transport (2014-04-04 to 2023-08-01). View full payment history →