BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
Interceptor/drainage works to six (6) NEAS sites in North East England.
The following is not exhaustive, reference should be made with other details as per individual site drawings:
1.remove existing gully, remove or bung existing pipes
2.Install petrol interceptors Install ACO multi-drain M100D to suppliers recommendation
3.remove bushes and trees
4.connections to proposed fuel and oil interceptors
5.connect to exiting drainage systems via new manholes
6.reinstate tarmac, block paving, concrete as required
7. suitably position new or replaced gully.