BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
The scope of work is as below:
1. To repair existing windows and add secondary glazing where required and affordable. The extent of repairs and surface treatment for the remaining units as required to maintain those units still in a relatively significantly dilapidated condition.
2. Where a window is clearly beyond repair, involving the majority of it needing to be replaced etc, then a like for like replacement.
The school is a Grade II Listed Building and works should be designed with a consideration of the special significance of the heritage asset, and in agreement with listed building consent and planning.
Targeted procedure was used.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Olivetti Group | - | £757,398 | - |