1. To remove furniture and clear fallen debris as required. To sheet up, strip, remove and dispose of the redundant artex and plasterboard ceiling. To include the removal of the fibreglass insulation and weekend working as required. To vacuum and decontaminate and carry out air reassurance testing.
2. To supply and install 12.5mm plasterboard to replace that removed. To tape, joint, sand and prepare for decorating. To supply and install MMMF insulating loft roll to replace that removed. To supply and apply 2 coats of white emulsion paint. All as discussed.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Scancross Limited | - | £10,000 | - |