BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
A47 / A11 Thickthorn Interchange
Galliford Try, as the East Region Delivery Partner are delivering the A47 / A11 Thickthorn Interchange project in the county of Norfolk in partnership with Highways England. The project will help relieve congestion at Thickthorn junction by providing two new free-flowing slip roads that will connect the A47 with the A11. The new slip roads will re-route traffic away from the junction and flow it under new underpasses.
The project has recently submitted a Development Consent Order to the Planning Inspectorate and the project is forecast to commence on site in early 2023 and will take around 2 years to complete.
Outline Scope of Works
Stage 1: Early Contractor Involvement. To provide technical and commercial input into the detailed design phase and to formulate the budget and programme for the works.
Stage 2: Construction. To provide all necessary supervision, labour, plant and materials required to undertake piling under the A11 & A47.
Timings
Deadline for Notifications of Interest 16:00 hrs on Tuesday 07th June 2022
Galliford Try procurement process
To secure work with Galliford Try, a supplier will need to pass the PAS91 onboarding process administered through Builders Profile. Details will be shared with shortlisted suppliers.
If this package is of interest to your company please contact our procurement team by e-mail on …@4projectsmail.com by the above deadline with your notification of interest and details of your capabilities.
No supplier information available.