The National Park Authority are looking for a suitably qualified and experienced contractor to undertake the design and installation of a new sewage treatment system at its Millers Dale site. The works include:
⢠Design of the system in the context of the parameters set out within the tender documentation and the information provided.
⢠Liaison with the relevant authorities to gain the necessary consents to undertake the works.
⢠Removal of the existing system and disposal from site.
⢠Installation of a complete new sewage treatment system suitable to meet the demands of the site and including (but not limited to): new pipe work as required, grease traps, sewage treatment plant, new soakaway.
⢠Full commissioning and handover of the plant and provision of operation and maintenance information.
To register your interest and receive tender updates please email …@peakdistrict.gov.uk using the contract reference 10804_STS_01 in the subject line.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| R.A.Dalton Ltd | 04880888 | £50,000 | - |