Works on Bar Street include:
⢠Removal of all street furniture to off-site storage or tip
⢠Excavation and disposal, or recycling of footway paving blocks & bedding to the specified design depth within the site boundary
⢠On-site identification, excavation and disposal of soft spots
⢠Reconstruction of the street to finished surface level including raising, lowering & where appropriate renewal of existing service covers to the new finished levels
⢠Laying block paving on a type 1 sub-base & sharp sand bed
⢠Taking up of existing gullys and lining of drains and put back gullies where appropriate
⢠Kerbing works
⢠Collection of some materials or items of street furniture stored from the Employer's storage location
Works on Aberdeen Walk include:
⢠Removal of all street furniture to off-site storage or tip
⢠Excavation and disposal, or recycling of paving flag and mono block bedding to the top of the concrete base slab within the site boundary
⢠On-site identification, excavation and disposal of damaged areas of the concrete base slab and reconstruction or repair of areas identified and/or removed
⢠Reconstruction of the carriageway through the scheme in bituminous bound material from the concrete base slab to finished surface level including raising or lowering existing service covers & where appropriate renewal of existing service covers to the new carriageway finished levels
⢠Laying stone paving flags & channel blocks on a mortar bed in footway areas including raising or lowering existing service covers & where appropriate renewal of existing service covers to the new footway finished levels
⢠Collection of some materials or items of street furniture stored from the Employer's storage location
Works on Newborough include:
⢠Removal of all street furniture to off-site storage or tip
⢠Excavation and disposal, or recycling of footway paving flags & bedding to the specified design depth within the site boundary
⢠On-site identification, excavation and disposal of soft spots
⢠Reconstruction of the street to finished surface level including raising, lowering & where appropriate renewal of existing service covers to the new finished levels
⢠Laying stone paving flags & blocks on a mortar bed or sharp sand bed (as detailed in the plans) in footway areas including raising or lowering existin
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Fox (Owmby) Limited | 00804642 | £290,953 | - |