The existing one-pipe heating system is in the process of being removed (by others) and the proposal is to provide new two-pipe heating infrastructure to the School. The new heating infrastructure will typically include new pipework, radiators, fan convectors, valves, pumps, headers, etc.
The proposal is to install a sealed system complete with expansion vessels and automatic pressurisation. The existing boilers are proposed to be retained and utilised as part of the system. The existing control panel is also to be retained and upgraded as necessary to suit the new heating plant configuration.