Work packages for the construction delivery services at Imjin Barracks for the Defence Estate Optimisation Portfolio. Lendlease are delivering works at Imjin Barracks on behalf of the Defence Infrastructure Organisation involving the reconfiguration and refurbishment of existing infrastructure and construction of new infrastructure to provide the MOD with improved Live/Work/Train requirements.
High-level Scope
Construction of foundations (Pile caps, ground beams, Strip foundations and Pad foundations) and ground floor slab with associated ancillary works to a MUGA pitch, 8nr Single Living Accommodation blocks, 2nr office buildings, 1nr storage building and 5nr other use buildings. (new build and extensions)
Earthworks associated with new build assets including retaining walls.
Additional information:
Minimum Compliance Requirements
Description 1: Lendlease Financial Performance and Accreditation requirements, Lendlease Global Minimum Requirements, Building Information Modelling requirements, BPSS