Debden BMS Upgrade - The works consist up replacing 9 BMS MCC panels and replacing Input /Output modules within 13 other MCC panels. The works include the following tasks:
1. Survey existing panels on site to ascertain space for new BMS modules
2. Re-work existing I/O to new smart I/O modules
3. Modify drawings to facilitate new I/O modules and submit for approval
4. Remove existing equipment and install replacement equipment
5. Make necessary programming changes to suit new I/O modules
6. Power panel and test.
7. Check point to point operation and sign off
8. Ensure graphics are operational.
9. Functional test each interface via BMS
10. Set system to work and monitor correct operation.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Schneider Electric UK | 02886434 | £412,439 | - |
Government spending data: This supplier has received £197,513 in 13 payments (over £25k) from Companies House, UKRI, Guy's and St Thomas' NHS FT (2015-12-17 to 2025-06-01). View full payment history →