The hall floor is to be completely taken up and a new, insulated slab constructed with a new composite timber floor finish installed. The first floor slab over the main reception area is to to be cut-away and a new reinforced slab cast, followed by new flooring.
If you require a site visit, please contact:
Sukhjinder Variah - (Concertus - surveyor) 07999043915
Isabel Webb (School Head) 01629 822457
No welfare facilities are available at this site.
No supplier information available.