To supply and fit one new chilled water pump no 1 in the Chiller Plant Room, change to a direct drive Lowara 37kw , commission as requested. The lead time is 8 working weeks.
To supply and fit one Danfoss inverter 37kw commission and leave in full working order
To remove existing pipework past isolation valves, supply and fit new valves and pipework to new pump
To modify power supply to condensate pump, control cables from BMS to new inverter, connection to new isolator and modify existing Trend control accordingly
Additional information: This contract was awarded via the Council's Best Value Form process as per North Yorkshire Council's Procurement and Contract Procedure Rules.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Aire Valley Rewinds Ltd | 07415780 | £40,327 | - |