BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
This contract has already been awarded and is being published for transparency purposes .
This amendment is being taken out of the overall contract value.
This amendment is to account for changes to the original research design of Housing First Pilot Evaluation. This contract amendment 04 covers to the contract and covers the following areas:
I. To extend the evaluation up until March 2023 due to delays in the implementation of the Housing First Pilots.
II. To account for the impact of Covid-19 on the pilots
III. The original ICF bid included estimates for the quantitative impact/longitudinal work and cost benefit analysis. This estimated work is now being set via this contract amendment.
IV. Adding a new objective for the "everyone in" policy.
The above is being done via two work packages.
I. The first is via Addendum 2 to Annex A, to reflect the reprofiling of the Pilots' delivery programme and the impact of COVID-19.
II. The second is via Addendum 3 to Annex A, to reflect the Next Steps Programme.
Additional information: The contract value is £2,260,000.00.
£1,106,420 being taken out of this overall contract value for this contract Amendment (Contract
Amendment 04)
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| ICF CONSULTING LIMITED | 03998136 | ~£0 estimated from lot values | - |
Government spending data: This supplier has received £269,183,114 in 814 payments (over £25k) from BEIS, DEFRA, FCDO, DLUHC, Department for Education and 7 more public bodies (2015-11-16 to 2026-02-18). View full payment history →