EKFB are seeking to appoint a supplier for the fabrication and supply of Weathering Steel Perforated Folded Plate Panels for the 900m long Bat Mitigation Structure to be built between chainages 76+675 & 77+600.
The scope for this package is as follows: 13,650No 8mm Weathering Steel Perforated Folded Plate Panels (3550mm long x see Design Brief). change
Lot 1 - Fabrication of Steel Panels
Lot 2 - Installation of Steel Panels (Optional)
Terms & Conditions - NEC3 Supply Contract
Programme - Start Onsite 18/07/2025 & Completion 27/03/2026 (Deliveries will be taken from March/April 2025
Execution Class - The supplier must be Execution Class 4 certified