Didcot Town councils have three buildings for which we would like to invest in Solar PV.
We recommend a site visit to allow you to truly understand each site, but this is not required:
We require from you:
Tier 1 panels appropriate inverter (such as Solar Edge or Solis),
Optimisers where appropriate.
Full installation including final connection to the board.
Scaffolding included
All appropriate paper work and approvals (G99 etc)
Online monitoring capability.
The Civic Hall: OX11 7HN
Approx. 25Kw of panels
Three phase
Flat Sarnafil Roof
Lightening Protection System in place
Two Storey Building
Willowbrook Leisure Centre: OX11 7AF
Approx. 55- 60Kw of Panels
Three Phase
Pitched Roof - Standing Seam
Lightening Protection System in place
7-15meters High
The Outdoor Service building: Edmonds Park: OX11 8QP
10-15Kw of panels
10/15Kwh storage battery ,
Single Phase
Pitched Roof , Standing Seams
Single storey Building
No supplier information available.