This Work Package defines the civil, mechanical and electrical installation works required to complete the DBB Blockhouse LV distribution installation from the existing D12 Automatic Transfer Switch to D1-PDU12, the associated isolation transformers and auxiliary distribution board. The Works include equipment handling and installation, civil works, cable containment, cable installation, glanding and termination, earthing and bonding, inspection, dead testing and support during UKAEA-controlled energisation.
No supplier information available.