BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
A call-off from Lot 1 of the Generation 4-TWO 2020-2024 Civil Engineering, Highways & Transportation Collaborative Framework (awarded 06 March 2020).
Works consists of a) Carry out jetting and cleaning of the culverts that are to be surveyed.
b) 2 foul water manholes to be surveyed and recorded at Fletchwood Road c) Vegetation (scrub and undergrowth) clearance for Ground
Investigation Surveys (GIS).
d) Traffic Management Support for GIS and pavement investigation works including carriageway pavement cores, window samples, observation pits and trial pits
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| MILDREN CONSTRUCTION LIMITED | 02136748 | £328,162 | - |
Government spending data: This supplier has received £449,601 in 4 payments (over £25k) from Department for Transport (2018-10-11 to 2018-12-18). View full payment history →