The footbridge currently present at this location is steel beamed with concrete block deck with timber handrails. In addition, a masonry abutment from a historic structure is present on the eastern bank.
The footpath at this location is CH 14/11.
These works are to include:
⢠Provision of photographic condition survey of bridge area and proposed access routes.
⢠Provision of current mid soffit height to invert.
⢠Removal of existing abutments and reprofiling of southern bank to an approximately 45Ⱐgradient.
⢠Stabilise reprofiled surfaces of southern bank using natural materials (e.g., rock rolls below water level and biodegradable geotextile above).
⢠Install new standard concrete pads.
⢠Supply and install 1No. 15m span standard steel framed/timber clad footbridge.
⢠Install steps either side of bridge with timber handrails.
⢠Install gates at either end of bridge.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Landmarc Ltd | - | £88,950 | - |